House Work
House Work 11092
bedroom
1/28
House Work 11095 House Work 11089 House Work 11085
Over the years, the house has required increasingly frequent painting to fight the growing mold.
House Work 11135
bedroom
2/10
House Work 11137 House Work 11142
bathroom
House Work 11145
office
House Work 11150 House Work 11153 House Work 11155
We are surprised to discover that the exterior walls are made of laid brick covered with mortar as workmen remove the mortar layer in the bedroom and office on the third floor.
House Work 11163
Workmen carry supplies directly from the street into the third floor office
House Work 11164
House Work 11232
2/13
House Work 11234
the walls are sealed and recemented
House Work 11246
bedroom corner
2/15
House Work 11247
office
House Work 11250
2/16
House Work 11252 House Work 11255 House Work 11260
2/21
House Work 11262 House Work 11267
2/27
House Work 11269 House Work 11273
wetter, 3/1
After a week of heavy rain, water is clearly leaking from somewhere above the ceiling into the new cement wall.
House Work 18878
new roof
2/15
Before the end of March, the new roof is completed and there are no more signs of leaking. We discover the downspouts from the three roofs may flood the sunken pits around the ground floor in heavy rain.